Water bottling line: plan from water source reach finished pack
For bottled water business, di filler alone no be di complete line. You need match di water-treatment scope, container supply, filling, closing, inspection and packing. Start with di water product wey you wan sell, di actual bottle and cap, then di good packed output you need. No assume say one supplier’s machine list covers every connection, utility or site job. This guide helps you turn those open questions into one scope wey suppliers fit review.
Check the hand hole with the pack wey shop go receive
Count full packs and loose bottles

Buy empty bottles or blow PET for your own site?
If you buy ready bottles, check delivery quality, storage space, handling and how bottles go enter di filler. If you blow bottles on site, include preforms, moulds, air supply and di connection from blower to filler. Compare both options with di same bottle drawing, neck and closure. Di choice no be machine price alone: incoming packaging, warehouse space and who go control each interface matter too.
| Bottle route | Scope wey must enter di review |
|---|---|
| Buy ready bottles | Receiving, protected storage, bottle feeding, sample quality and di transfer into filling. |
| Blow PET on site | Preform and mould qualification, blowing equipment, specified air utilities, bottle handling and controls. |
If water bottle size change, how you go count loose bottles wey never enter full pack?
If the new pack carry 12 bottles, six loose bottles for packing table no be half pack wey storekeeper don receive. But if nobody write those six down, the next shift fit think say water disappear for the line.
Mark where the count start
Agree whether una dey buy capacity in sealed packs or good bottles at the inspection point. Write the pack size, batch code and time. Count any loose bottles for the table before the test start, so old stock no go enter the new result.
Close the count when time reach
Suppose 40 full packs of 12 pass final check and six bottles still dey the table. Write 40 accepted packs, equal to 480 packed bottles, plus six loose bottles waiting. If those six join another pack later, enter that pack under the time e pass the agreed point.
Make supplier show the unit beside the promised figure. Then the person wey sign for warehouse fit trace every pack without guessing.
Convert bottle target to water demand with clear units
Planning example only, no be machine rating:5,000 bottles per hour ×0.5 litre na2,500 litres per hour inside those bottles. This calculation no include every rinse, startup loss or cleaning demand. Also, filled bottles no automatically mean accepted finished packs. State shift hours, planned stops, bottle size, pack pattern, counting point and reject rule before comparing quoted bottles/hour. Ask suppliers which product and format their speed statement covers.
One water line, different bottles: which change parts enter di price?
Before you buy water bottling line for different bottle sizes, turn flexible line into one clear format list. Name di bottle body, neck, cap, label and final pack for every SKU. Make each supplier mark wetin dem include, wetin needs adjustment or another part set, and wetin never pass trial. Na this same list you go use compare offers.
| Wetin go change | Evidence to send | Wetin offer must name |
|---|---|---|
| Bottle body | Drawing revision, dimensions and actual samples for every shape. | Guides, starwheels, height adjustment and transfer points wey need review. |
| Neck and cap | Neck finish, thread, support ring and matching cap drawing. | Cap feeding, closing parts and closure checks for di exact pair. |
| On-site PET blowing | Preform, mould and agreed bottle sample. | Which mould sets, tools and new-bottle trials enter di supply scope. |
| Label and final pack | Label size, code position, bottle count and pack pattern. | Change parts, settings, inspection and trial material for labeller and packer. |
| Part sets | Format list and spares list. | Part numbers, quantities, marks, storage and future formats wey get separate price. |
Compare changeover time with di same start and finish
- Record di time of last accepted final pack A and first accepted final pack B. Record di later time wey steady running gets confirmation separately, using di observation period and conditions wey everybody agrees.
- Record removal of old materials, part replacement or adjustment, recipe selection, new-material loading and acceptance checks separately. Name how many trained people and which tools di trial needs.
- Count water, bottle, cap, label and wrapping losses plus startup rejects through di end of di agreed observation period. Write site checks wey remain, who go do them and who go supply trial materials.
Mechanical changeover and product or hygiene approval get different scope. Bottle wey moves through machine no prove say water don qualify for release. Ask supplier to separate machine setup from cleaning and quality checks wey your actual product and site require.
Same bottle neck mean say no change parts?
No. Bottle body, height, label and pack fit still change. Make supplier review di whole route and list parts for di exact bottle-and-cap combination.
Every future bottle design don enter di quote?
Only formats wey di offer names and covers. For another design, ask which review, samples, parts, software work and trial fit bring extra cost.
Why water fit finish when treatment flow look enough?
Separate water wey enters good product from other factory uses. Bottles/hour and litres/hour cover different boundaries. Before you choose treatment, tank and pump, list demand by time, required water quality and which users go run together. Daily total alone fit hide peak shortage.
| Demand boundary | Wetin quotation and trial must define |
|---|---|
| Water reaching filler | Bottle volume × filling rate with correct units. Record startup, rejected product and flushing separately; no count one loss twice. |
| Rinsing and cleaning | Equipment, batch water, timing, quality and simultaneous use. No use one universal water-per-bottle allowance. |
| RO if you select am | Confirm whether flow means feed or permeate. State recovery basis, concentrate flow and reference conditions against actual water analysis and variation. |
| Tank and pump | Usable level range, refill time and pressure when users run together. Buffer no fit cover continuing supply shortage. |
Request water balance wey names supply and discharge boundaries, reference conditions, measuring points and responsible suppliers. Compare treatment trial with actual site before acceptance. Flow calculation no replace product-water quality approval or cleaning validation.
Prepare evidence before you request final quotation
Send source-water analysis with sample date and known variation, intended product specification, bottle and cap drawings, physical samples, target accepted output, final pack, site layout, utility information and destination. Mark unknowns. Ask di offer to separate machines, change parts, connecting equipment, installation, local work and acceptance trials. Agree trial materials, duration, good-pack counting point and how stops or rejects go enter di record. Keep gaps for later site tests in writing; moving bottles in a video no prove di entire project.
Email di water-line project team sales@allottech.comYour water line dey stop often? Trace di first stop before you buy faster filler
If full bottles pile up before di labeller, e fit make di filler stop. Watch di line with di same bottle and pack for one agreed period. Write wetin happen first and where bottles wait. Di last alarm no always show where di wahala start.
| Wetin operator see | Wetin to write down | Wetin to check before purchase |
|---|---|---|
| Filler dey wait for empty bottles | Check when empty bottles stop to reach di filler. Compare di times with di feeder or blower log. | Check bottle supply and transfer. Ask how di proposed machine go reduce that loss. |
| Full bottles dey gather after filling | Record where di queue start, which machine dey wait, and when di filler get stop signal. | Price repair for di slow station and filler replacement separately. Test how di machines go restart together. |
| Di line dey move but plenty packs get rejected | Separate bottles wey inspection remove from pack rejects. Keep samples for quality checks. | Price di fix for di defect. If filler go change, name who go test di retained inspection system with am. |
| Two offers promise more bottles per hour | Make both suppliers name di pack format, test time, counting point and which old machines go stay. | Compare good final packs per agreed period and record downtime and rejects on di same basis. Ask which interface work get separate price. |
For each stop, send di time, wetin happen first, where bottles wait, when good packs start again, and how many packs quality reject. Add di good-pack target so supplier fit quote di job wey address di loss.
If faster filler pass test for supplier factory, e don prove say my line go give more good packs?
That trial fit show how di filler work under di test conditions. Agree separate test for your site with di machines wey go remain and di actual bottles and wraps. Count good packs after packing.
Check how space, power, water and air go reach equipment wey you add
If di filler clock and labeller clock no show di same time, write di difference beside di alarm logs so supplier fit match wetin happen first.
Ask for price to check why your water line dey stop sales@allottech.com
The hand hole tear when shop receive bottled water. Which carton una suppose test?
Empty carton fit look strong for sample table. Once full water bottles enter, the size of the hole, how carton wall fold and wet condition for delivery fit affect wetin receiver see. One torn hole no show on its own whether board quality or carton making cause am.
Keep the torn side and one good sample
Write bottle size, number inside, carton code and which side tear. Check whether the cut line don already open before delivery and whether the area around the hole wet. Take picture before anybody flatten the carton.
Agree the receiving trial with the shop
Use the proposed filled pack and the shop's approved handling method. If shop no dey use hand holes at all, record the way dem really move the carton. Compare samples wey get the same board and bottle arrangement so una fit tell wetin change.
Put the approved carton drawing and trial note inside the order. If supplier change the cut or board later, buyer go know the exact pack wey need another trial.
If water meter reset for middle of test, how buyer go know how many litres pass?
For one shift, treatment operator fit write the first reading before another person reset the total. If buyer just subtract the morning number from the closing number, the answer fit even come out negative while water still dey flow.
Keep the last reading before reset
Suppose the total move from 4,100 reach 4,450 litres. After reset, e start from zero reach 280 litres. If record show both sides of the reset and no gap, na 350 plus 280, or 630 litres, pass that meter for the test.
Check wetin the meter dey count
Write the meter number and mark the pipe for the trial sheet. If na treated-water pipe e dey, the 630 litres no tell you how many sealed bottles warehouse accept. Collect the pack count and bottle size for that same period.
If nobody get the reading before reset, mark that part as missing and agree how to repeat the measurement. Make buyer and supplier sign the record wey dem actually fit check.
Questions
Must every water line get bottle blower?
No. A line fit use suitable bought bottles if receiving, storage and feeding are planned. On-site blowing adds its own preform, mould, air and integration scope.
Bigger tank fit fix small treatment unit?
Only for a limited interruption wey calculation supports. Compare usable volume, draw rate and refill schedule. If demand stays above supply, di tank go still empty.
One water report enough to settle treatment?
Na starting evidence. Identify source, sample date, operating range and known seasonal changes. Record missing evidence and review treatment against intended product requirements.